If your cargo uses Durban, or you sell into a factory that does, the bottleneck has got worse than the delays reported earlier this year. On 16 November 2026, Moneyweb reported that automotive-component manufacturer Metair may have to invoke force majeure in its supply contracts because vessels are spending 14 to 20 days at anchorage waiting to unload at Durban Gateway Terminal (DGT), which runs Durban Container Terminal Pier 2.

This is an update to the picture we set out in October, when we wrote about Durban’s then 11-day queues. The numbers have moved, a listed manufacturer has put a cost on them, and the festive peak is still ahead. Here is what the latest figures say, where they differ, and what shippers, shipping staff and manufacturers should do.

What Metair is warning about

Metair CEO Paul O’Flaherty told Moneyweb the delays started in July and have deteriorated so that ships now wait 14 to 20 days at anchorage. The group’s shares fell more than 35 per cent on Friday after that warning, the paper said.

“There’s no end [to the crisis] in sight, in my view,” O’Flaherty said. He described a pattern of air-freighting components, then working heavy overtime, to keep customers’ production lines running. “There can never be an open cheque book. I can weather a certain storm, but I cannot weather it endlessly.”

Metair said the extra cost of air freight, safety stock and overtime could amount to 20 to 25 per cent of its reported EBITDA for last year, before exceptional items. That is the company’s own estimate of a cost impact, not a figure for every shipper.

What the terminal and other official sources say

The delays are not only a manufacturer’s complaint. Hapag-Lloyd’s Week 45 Africa operational update (last updated 6 November 2026) put waiting at Durban Pier 1 at 6 to 9 days and Pier 2 (DGT) at 12 to 14 days, to be monitored case by case because of weather. Everstream Analytics, in a 12 November port congestion report, cited an average wait at Durban of 7.54 days, with Pier 1 delayed and two cranes likely out of service for some time.

Those numbers measure slightly different things (anchorage time experienced by one cargo owner, a carrier’s berth-delay ranges, and a 7-day average). They all point the same way: Durban is running well behind a normal call, and Pier 2 is the tighter of the two container facilities.

DGT CEO Javier Lancha told Moneyweb the terminal does not dispute that customers have faced disruption. He said problems followed DGT’s move to the Navis N4 terminal operating system, which affected container handling and truck bookings, and that equipment failures and limited crane availability added to the backlog. Lancha said the operating system has since stabilised, that DGT is meeting the National Association of Automotive Component and Allied Manufacturers this week, and that extended storage for import boxes has been used to get containers out of the yard.

Transport Minister Barbara Creecy said a return to previous performance is expected between December 2026 and February 2027, supported by additional equipment arriving in December, Moneyweb reported. O’Flaherty’s question was the obvious one: what if the crisis runs past February?

DGT was partly privatised in January 2026, when International Container Terminal Services Inc (ICTSI) took over operations and management in a 25-year partnership with Transnet, which retains a 51 per cent stake. After the summer peak, DGT says the next phase includes more than R2 billion of capital investment over three years, including straddle carriers and an initial 16 hybrid rubber-tyred gantries. That is a future programme, not a fix for cargo already on the water.

Truckers have also reported spending up to 22 hours at the terminal despite valid appointment bookings, according to the same Moneyweb report. Yard and landside congestion are part of the same problem as the queue at sea.

The Southern African Association of Freight Forwarders said the situation “requires intervention commensurate with its scale, urgency and national economic consequences.” Durban Chamber of Commerce and Industry CEO Palesa Phili said performance had deteriorated sharply in the last two months after a period of relative stability.

What it means if you use Durban

1. Build 14 to 20 days into your plan, not a weekend buffer. If your box is on a vessel still waiting for Pier 2, a “scheduled arrival” on the bill of lading is not a delivery date. Speak to your line and forwarder about the actual berthing prospect, and tell your own customers early.

2. Decide, in writing, who pays for the extras. Air freight, storage, detention, demurrage and overtime add up quickly. Check your sale contract, Incoterms and any force majeure clause before you assume the other party will absorb them. Metair’s warning is a reminder that those clauses are being read carefully this month.

3. Ask which terminal you are actually using. Pier 1 and Pier 2 are not the same queue. Hapag-Lloyd’s ranges differ by several days. A booking that can move to a less delayed facility, or to Cape Town, Gqeberha (Port Elizabeth) or Coega, may be worth comparing, but those ports have their own weather delays (Hapag-Lloyd cites wind at Cape Town and wind and rain at Port Elizabeth and Coega).

4. Do not treat a system “stabilisation” notice as a cleared backlog. Even if Navis N4 is now stable, ships already at anchor still have to be worked off, and the festive peak is coming. Keep checking the carrier’s operational update, not only the original schedule.

5. If you truck boxes out of Durban, book early and expect landside waits. A 22-hour terminal stay on a valid appointment is expensive in diesel and driver time. Confirm the appointment, the container’s ready status and the pre-advice before the truck leaves the park.

What to watch next

  • Whether additional equipment due in December actually arrives and cuts the Pier 2 queue.
  • Any official revision of the December-to-February recovery window.
  • Carrier omissions or blanked sailings that skip Durban and push cargo onto later vessels or other ports.
  • How extended import-storage rules affect your free time and your bill if you cannot collect promptly.

How Septmax can help

Septmax Logistics helps importers, exporters and businesses plan routes into West Africa and connect cargo that moves through other African hubs. If you have a shipment going via Durban, or you are comparing a South Africa call with a direct West Africa service, we can help you read the latest schedules and build a more realistic timeline.